Let me start by asking you a few questions about your attitude towards administration. We all know that some of us are better organised than others.
Even so, take a moment and answer the following questions;
Are you one of those PMs that is excellent at planning and managing what others do, but not so good at managing your own tasks and time?
Do you feel as though everything is under control, as you know all that is going on and therefore, there is no need to review or update the risk register, etc.?
Have you learned something useful and incorporated the lesson into the project, and so there is no need to document?
Are you lazy?
Buried in Paperwork? Let Derek Bland and PM-Partners help you sort out your priorities.
None of the advice below excuses the lazy – sorry, guys.
There will be some of you that need to adhere to a PM method that is document heavy, and the application is not proportionate to the size and complexity of the project. It may be that there is no company-wide method or project, programme or portfolio management (P3M, for short) standards being applied. The advice below will not get rid of this problem, but may help you to organise your time. p3m global is a Portfolio, Programme and Project Management consultancy and training company that is involved with the design and implementation of project management methods; therefore, we can help define and/or streamline your processes.
The advice below should be adjusted to your own needs and those for the project.
1. KNOW WHERE IT IS – BE ORGANISED: It is essential to be organised form the start. Ensure you have a good folder structure that helps you to find documents easily as this will save you time. An example would be to have a folder for; strategies, registers, schedules and work packages and a folder for products to be produced. Let’s be honest, communication is driven by email and so it is as important to have a similar folder structure for your emails.
2. KNOW WHAT IT IS AND WHAT THE CURRENT VERSION IS: It is imperative that you version (yes, it’s a verb in this case!) your documents. A good practice for documents that are being worked on (WIP) are to use a decimal place and once approved/signed off, the version is rounded up to a whole number. This process is then repeated for all subsequent versions. Example of WIP versions, v0.1, v0.2 etc. Once signed off it becomes v1.0, followed by the next version earning a label v2.0, and so on. Another option for documents or registers is to use a date format. I like to use YYMMDD. Therefore, my Risk Register will be Risk Register, PMP Project 140131. This ensures that it will always be the latest version. Make sure you have a good naming convention for all project documents and ensure that all of those producing product documentation follow these protocols.
3. KNOW WHEN YOU ARE GOING TO DO TASKS – BE DISCIPLINED: We all know that projects in a fast-paced and or complex state can throw up urgent issues. However, it is important to schedule set times so that you can review documents – even if only a quick check – to verify that they do not need updating. Make a recurring schedule item in your calendar and add a checklist of activities to the calendar appointment. Break-up mundane activities into small manageable tasks. A simple example* might be;
4. BEWARE THE MEETING, ESPECIALLY THE IMPROMTU ONES: Meetings are necessary and can aid greatly in communication and assist in team building. However, avoid agreeing to a meeting if you feel it is for said meeting’s sake. I once worked on an extremely large Government Project. The main project team took up one floor, with additional staff distributed thorough the building. The floor was open plan and so it was easy to see what was going on around you; ergo, it became easier to be distracted. I estimated that around 35% of my day could be taken up with impromptu meetings or chats at the water cooler. Do not be afraid to say that you have something urgent that you are working on and arrange a time to meet to discuss. However, consider if the meeting is really necessary or whether the person just wants a chat or the person may simply want to get something off of their chest. Although this may not be a priority for you, you should try and find some time to listen to concerns, because you never know: something productive may come out of it.
5. WHAT HAVE YOU LEARNED: I am not just referring to lessons to be logged in the Lesson Log; rather the way that you work. Ensure that you actively audit yourself by taking time to reflect and think about;
How have you been perceived in a particular instance; did you try something new which worked, could you have communicated better? Did you provide information to the correct level of detail and in the correct format?
How well have you managed your time? Could you have performed some tasks more quickly without compromising quality? Were some of the meeting necessary or did they drag on too long and how could you improve this the meeting next time? Remember you are the Project Manager, many of the team will want to learn from you. Anything that you can learn for yourself needs to be acted upon and so log it – learn it – embed it.
* – Please note that the above list is a very simple example and does not negate the need to update or review project documentation as required. The very act of recording a risk or issue often promotes ideas on how best to deal with it.
Derek Bland is Project Management Consultant & Trainer at p3m global. His experience includes consultancy on design and delivery of bespoke Project Management methods, conducting Project Audits and advising PMs on best practice improvements. As a trainer, Derek delivers on a variety of Project Management Courses, including PRINCE2 and MSP.
Estimating is undoubtedly one of the most complex tasks in project management. There are various, damning statistics published on the failure of projects to deliver within time and/or cost and suffice to say they don’t look good. This fact remains despite the various tools and techniques at the project manager’s disposal. The list of pitfalls below is neither exhaustive nor a panacea to answering all of your estimating challenges; rather, it’s a checklist that you should keep in mind when planning and estimating. One scenario that cannot be reconciled by the advice below is where a high level guess is made by management and expected to be adhered to without more detailed scoping and activity planning. This top-down approach can often be aligned to the “just do it” (JDI) approach – “here’s your budget, JDI”. You reply, “But what about, but what about, but what about…” At this point you receive some great advice: “work harder, work smarter, work faster” Sorry, but I can’t help you there. Just remember: if any of your constraints are not balanced, then something’s gotta give. Pitfall 1: Uninformed or partially informed Guessing or Ball parking. How much will it cost to build a five-bedroom house? The answer is, it depends:
What is in scope?
What size does the house need to be?
Does it include landscaping the garden?
Does the project include decorating and light fittings and, and…?”
Whilst all of this may seem obvious, accurate estimates are reliant upon sufficient understanding of the requirements. Be especially careful when you hear the words, “give me a ballpark now, I won’t hold you to it” – get this in writing!!! I must admit to having asked for ballparks on many occasions both for projects and in home life. I recently asked several builders how much it would cost to build a 2-storey extension of X square feet. However, when I ask for a ballpark, I accept that this is based on a very loose specification but at least it provides me with a range of figures to enable me to make an initial decision on whether to investigate further. Let’s be honest, it is also not easy to hold a builder to an estimate.
Pitfall 2: Failure to help the customer define what they want and how much they are willing to spend. Many customers have a high level understanding of what they want but are not always able to articulate the detail of what they want or more precisely what they need. It is one of the project manager’s responsibilities to help the customer to define what they want/need. The definition of requirements needs to be coupled with how much the customer is willing to spend. It would be nice to hear, “money is no object” but this is extremely rare if not non-existent. Therefore, there is no point defining the building of an ocean liner when the customer is only willing to pay for a dinghy. I have seen the results of a detailed tender which took many man hours, only to discover that the customer’s budget was a fraction of what the scope covered by the tender would have cost.
Pitfall 3: Misunderstanding quotes and estimates. A quote is a fixed price whereas an estimate is an approximation. Where a customer asks for a quote, it is essential to ensure that you fully understand what you are quoting for. In the example of the five-bedroom house above, we would need to know, amongst many, many other things, if the quote should include the decorating, landscaping of the garden and much more. So often, fixed-price contracts are agreed without sufficient investigation and definition of the requirements. Significant caution should be applied especially where you or your organisation are keen to win business. In this instance it is imperative you spend a little more time detailing and agreeing the scope at the start. The additional time spent up front could save you from a loss making project later. I have been involved in projects where the scope was not sufficiently defined and ended up costing us considerably more than it should have.
Pitfall 4: Not identifying the activities/tasks. Larger projects are very difficult to plan in detail at the start. Where this is the case it is important for all parties to understand that the margins for error are greater and therefore, the more change control and wiggle-room or tolerance that is required. Remember, the more you can break down the activities the more accurate your estimates will be. One of the biggest mistakes made is in failing to identify project management activities required to deliver the project. This includes not only the Project Managers activities but those of the teams such as reporting progress, meetings, phone calls and emails. Consider researching Maximum Available Productivity (MAP) to get a better understanding of how much of a day is spent on project work and how much on other tasks. I was involved in a project where the customer was a global organisations and the business we did with them very important to the company. Prior to joining the project a fixed-price had been agreed. The deliverables had not been sufficiently defined and so what may have been initially envisaged and what the customer wanted were a little out of sync. In addition, whilst the key stakeholder was great to deal with, they were very particular and would ask for multiple minor changes after the initial review rounds. Some would only take an hour or so but when you add in the emails, phone calls, meetings, reformatting and other activities, it adds up to quite a significant number of days.
Pitfall 5: Good Padding and Bad Padding. Before you shout, “no, padding should be allowed, it is always bad”, let me clarify what I mean. Good padding is taking into account activities that do not easily sit on a projects schedule and that these need to be allowed for when estimating. Bad padding is where a PM automatically adds time so as to come under budget knowing that the quote is excessively padded. Whilst this may work on one or two projects you will eventually get caught out. I am usually a cautious PM as previous experience has shown me that to immediately agree to time and cost estimates without fully understanding each deliverable and the tasks, is at best poor and for experienced project manager’s, dare I say it, unprofessional. This pitfall should be considered with almost all of the other pitfalls in this post.
Pitfall 6: Failure to learn lessons. I think it is fair to say that there are many project managers that research lessons from similar past projects. However, in my experience, sadly these are in the minority. It is imperative that you look to lessons learned from similar past projects to ensure that you learn not only estimating errors but other issues that you may be able to avoid and that will save you time and money. Learning lessons is equally important during your project, especially if it is a long and/or a multi-staged project. Lessons from earlier work can be applied to estimating future tasks to ensure improved accuracy. I have worked for companies that make the same mistake time after time and wonder why there projects are always over time and budget.
Pitfall 7: Not knowing a reasonable cost. There may be elements of work on the project hat are unfamiliar to you and your team and that require the services of an external supplier. Where this is the case, you need to ensure you do your homework and know what a fair rate is. I was looking on eBay recently for fuel containers, and was amazed at how the price differed for precisely the same container. The lowest price was £9.99 and the highest £29.99. I am serious, this was for exactly the same product.
Pitfall 8: Failing to include the subject matter expert (SME). It is essential to include the SME when estimating. After all, they will be the ones that know the work or managing the work and therefore, their invaluable experience is a crucial input when planning and preparing estimates. I have experienced both the good and the bad. In one organisation I worked for, bids from sales would include input from the experienced project manager and SMEs to ensure an accurate quote was provided. In other organisations, the sales and other management have decided on a time and cost without full consultation with the SME. This actually resulted in the deliverables taking longer and ultimately costing the supplier more money. One reason for this may be that their ego dictates that they should know. Why should they know? A manger will not always understand the minutia to create a deliverable and should make the use of the experience of their team. Good managers and leaders understand that no one has a monopoly on ideas and utilises and publicises ideas from within their team.
Pitfall 9: Failing to allow for bias, pessimistic and optimistic. The project manager needs to be aware of their own bias and that of management and the project team. Pessimistic bias is where an individual tends to add additional time as they always consider it will take more time or something will go wrong. Let’s not malign this character too readily. They often have valid reasons for this approach, most likely gained form the experience of the JDI approach mentioned above or they can see vast chasms in the detailing of the scope. This needs to be balanced against the Optimistic bias or “rose coloured spectacles”. This happy-go-lucky character tends to believe that everything is easy or simple and that more can be achieved than is realistic. An example is where an SME is asked how long it will take to perform a number of activities. They quote based on them performing the task and in perfect conditions, without considering the experience of the individual(s) involved in performing the task. The most dangerous of the optimists are those that want to be seen to have a “can do attitude”. A “can do attitude” is essential for a project manager, but as with many of these thrown-around terms, it needs to be balanced with realism. I recall one particular colleague that would always say, “Oh, I can knock that up in a couple of days”. Whilst this was occasionally achieved, it was rare for the original estimate to be met. They also had a high sick rate without having any specific medical condition. There is also the poor soul who wants to impress and so underquotes with the intention of working almost 24/7. Invariably, this person will burn out and again watch their sick record.
In conclusion, estimating is a tough challenge. This post is not intended to cover all potential estimating pitfalls, but does provide you with a list of what I have found to be some of the main problems in estimating. Keep these in mind and with the use of this advice and the right estimating techniques and tools, I am convinced your estimating will improve.
Derek Bland is Project Management Consultant & Trainer at p3m global. His experience includes consultancy on design and delivery of bespoke Project Management methods, conducting Project Audits and advising PMs on best practice improvements. As a trainer, Derek has worked in PRINCE2 and MSP environments and delivered on a variety of project management courses.